Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Milestone

Owner

Deadline

Status

  1. Status
    colourYellow
    titlein progress
    Completed 3rd party Pen Test

  2. Status
    colourGreen
    titlecomplete
    Create new, private Vulnerability Tracker (since Jira config hasn’t proven entirely trustworthy for embargoed issues we don’t want to make public yet)

  3. Status
    colourYellow
    titlein progress
    Completed fixes for issues found during 3rd party Pen Test

  4. Status
    colourYellow
    titlein progress
    Triage list of unresolved vulnerabilities into the new, private Vulnerability Tracker

  1. Add default support for Authentication Module into O3 RefApp.

Samuel Lubwama & Org Administrator

Status
titlenot started

  1. More detailed sample Implementer Guides for implementation security maintenance.

IntelliSOFT Consulting Ltd.

Status
colourYellow
titlein progress