- Sprints are focused on one topic, and are either 1, 2, or 3 weeks long (as appropriate for the topic at hand)
- Each sprint should include 2+ OpenMRS developers. We may occasionally have multiple sprints going simultaneously, as not everyone needs to be assigned to every topic.
- We should always try to decide on a sprint topic 4 weeks before it starts.
- Each sprint should have a release in JIRA. The tickets in the release should be partially organized one week before the sprint. They must be finalized by the day before the sprint.
- The scope and tickets are locked-down once the sprint begins.
- To keep improving, each sprint ends with a retrospective look at what did and did not work with the previous week.
Schedule
2011
April
- 18th - 25th: Core bug fixes
- 4th - 18th: Module tickets
...