I think the above functionality would finish in the summer period . These implemented functionality would complete the HRModule.
HR-Module Proposed Timeline
Date | Task |
---|---|
1st May -15th May |
...
I would be busy with my exams | |
17th May - 22nd |
...
May | Create the table |
...
definitions and the entities |
...
for the same |
...
23nd May - 5th |
...
June | Build the service class, create methods in the service class ,provide methods in the service class and provide CRUD operations for all the entities |
6th June - 8th June | Testing of service class |
9th June - 11th July |
...
Design screens for managing certificate, competency, leave ,evaluation , discipline, education and injury roughly 4 days for each screen | |
12th July - 16thJuly | Creating functionality for ILO codes |
...
17th July - 27th |
...
July | Buffer period for any unpredictable delay |
...
28th July - 10th |
...
Aug | Dynamic generation of reports |
...