I think the above functionality would finish in the summer period . These implemented functionality would complete the HRModule.

HR-Module Proposed Timeline

Date

Task

1st May -15th May

...

I would be busy with my exams

17th May - 22nd

...

May

Create the table

...

definitions and the entities

...

for the same

...

23nd May - 5th

...

June

Build the service class, create methods in the service class ,provide methods in the service class and provide CRUD operations for all the entities

6th June - 8th June

Testing of service class

9th June - 11th July

...

Design screens for managing certificate, competency, leave ,evaluation , discipline, education and injury roughly 4 days for each screen

12th July - 16thJuly

Creating functionality for ILO codes

...

17th July - 27th

...

July

Buffer period for any unpredictable delay

...

28th July - 10th

...

Aug

Dynamic generation of reports 

...