I. After a ETL is performed, now for Second Stage we require two component
     1. EDW
     2. OpenMRS Predictive Analysis Module.
II. Performing Predictive Analysis - we can use Apache Mayhout for implementation.

 Mockup UI

Mockup
Version3
Width600
NameQuery Editor

Mockup
Version1
Width600
NameTabularView

Project Timeline

  • 19 May -  22 May: Study MySQL DB Transformation using JSP
  • 22 May - 26 May: Study  Direct Web Remoting and Spring Controller
  • 26 May - 4 June. DWR implementation and back end designing using JavaScript and Java.
  • 5 June -  8 June:  Make a Web Wizard similar to mentioned Mockup UI.
  • 9 June - 12 June: jQuery Drag and Drop support for columns in table.
  • 12 June - 14 June: Hadoop, Hive, Thrift Study, Setup, Resource Collection.
  • 14 June - 15 June: Testing and Implementing Datawarehouse Login (Backend and Frontend).
  • 16 June - 22 June: Transform and Load Table from MySQL to  Datawarehouse. Implementing various Joins.
  • 23 June - 29 June: Loading data to Hive using ssh and thrift
  • 30 June - 6 July: Test and execute Hive queries using ssh, hive-jdbc and thrift in OpenMRS Module.
  • 7 July -  13 July: Get results of queries on page in interactive manner.
  • 14 July - 28 July: Studying Apache Mahout, Implementaion and Web Interface
  • 28 July - 18 August: Code Fixing, Bug Solving and Later Finishing

...