...
Reference Application is a state of the art implementation of OpenMRS, which may serve as a solid base for new implementations. It is designed using the latest UI 2.x and App Framework and is related to
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
- Add User Account Manager tool see https://tickets.openmrs.org/browse/RA-61
- Manage Locations (including tagging those location, adding and editing location attributes)
- Add advanced settings management tool(s), add custom pages for managing specific global properties Settings (formerly Global Properties from platform 1.8 downwards) (e.g. all the security.* GPs together nicely in a Security Settings page)
Therefore, this project would involve:
- User management app
- Location management app
- Advanced Settings
- Records management app (extra credit)
Extra Credit
- Add a new page that lets you see all data associated with a patient/visit/encounter record (including voided data) in some ugly table format, mainly for an administrator to be able to unvoid data.
Design
Hierarchy of various tools and apps in Administration module
Administration Tools will be built on UI Framework, which form the base of reference application. The module will have standard module dependency on “uiframework” module. The UI Framework is built on Spring MVC and implements Groovy templates for views. So, the views will be provided by .gsp files. Existing fragments of UI 2.0 will be used and new fragments will be created wherever required.
Deliverables
Communication Plan
Weekly meetings - ~10 am EST every Wednesday
Emails, IRC
Project Timeline
- 21 April – 15 May : Understand App Framework and UI 2.x deeply, learn required technologies, get to know the mentors, prepare working on the project
- 19 May – 26 May : Will not be available due to the final exams at university
- 26 May – 22 June : Create module, implement User Manager
- 23 June – 27 June : Midterm evaluation
- 28 June – 15 July : Implement Location manager
- 16 July – 1 Aug : Implement Advanced Settings + Record Manager (possibly)
- 2 Aug – 7 Aug : Finalize UI
- 8 Aug – 18 Aug Write tests, prepare documentation
- 19 Aug – 22 Aug : Final evaluation
UI Mockups
1. 1. Administration App Homepage
Mockup | ||||
---|---|---|---|---|
|
2. User manager Dashboard
Mockup | ||||
---|---|---|---|---|
|
3. findUser App
Mockup | ||||
---|---|---|---|---|
|
4. addUser App
Mockup | ||||
---|---|---|---|---|
|
5. Location manager Dashboard
Mockup | ||||
---|---|---|---|---|
|
6. locationTags App
Mockup | ||||
---|---|---|---|---|
|
7. Advanced Settings Tool
Mockup | ||||
---|---|---|---|---|
|
8. Security Settings tool
Mockup | ||||
---|---|---|---|---|
|
9. Record Manager tool
Mockup | ||||
---|---|---|---|---|
|
Resources
- Getting started
- New UI framework
- Using new UI framework in your module
- UI framework step by step tutorial