Panel | ||||
---|---|---|---|---|
On this page:
|
...
From | To | Topic | Product Owner | Lead Developer | Developer Effort Estimated | Kickoff Meeting Held? | Goals Outlined? | Retrospective Completed? |
---|---|---|---|---|---|---|---|---|
2016-11-01 | 2016-11-15 | Open Concept Lab Sprint 2 | Jonathan Payne | raff | ||||
2016-02-14 | 2016-02-23 | Platform 2.0 Beta - RESTWS | OpenMRS Community | Mayank Sharma | No | Yes | ||
2016-01-17 | 2016-01-31 | Platform 2.0 Beta | OpenMRS Community | Mayank Sharma | Yes | Yes | ||
2015-07-27 | 2015-08-07 | Admin UI | TBD | Wyclif Luyima | No | Yes | No | |
2015-01-08 | 2015-01-25 | Registration v2 | David DeSimone | Wyclif Luyima | Yes | Yes | No | |
2014-11-10 | 2014-11-14 | OpenMRS Platform 1.11 pre-alpha-release testing and bug fixing | OpenMRS Community | Kaweesi Joseph | No | Yes | ||
2014-10-27 | 2014-11-10 | Working on OpenMRS Platform 1.11 Release Test Failed tickets | OpenMRS | Kaweesi Joseph | Yes | |||
2014-10-12 | 2014-10-26 | Testing OpenMRS Platform 1.11 Release Tickets Sprint 3 - 2014 (iteration 3) | OpenMRS community | Kaweesi Joseph | Yes | |||
2014-10-07 | 2014-10-21 | Allergies (Iteration 4) | Jonathan Teich, Shasha Liu | Daniel Kayiwa | Yes | |||
2014-08-14 | 2014-08-28 | Testing OpenMRS Platform 1.11 Release Tickets Sprint 2 - 2014 (iteration 2) | OpenMRS community | Kaweesi Joseph | Yes | |||
2014-07-30 | 2014-08-13 | Testing OpenMRS 1.11 Release Tickets (iteration 1) | OpenMRS community | Kaweesi Joseph | Yes | |||
2014-09-01 | 2014-09-15 | Allergies (Iteration 3) | Jonathan Teich, Shasha Liu | Daniel Kayiwa | Yes | |||
2014-03-18 | 2014-03-31 | Order Entry (Iteration 5) | JSS, KenyaEMR, OpenMRS | Wyclif Luyima | Google Hangout | Yes |
| |
2014-02-25 | 2014-03-17 | Order Entry (Iteration 4) | JSS, KenyaEMR, OpenMRS | Wyclif Luyima | Google Hangout | Yes | Yes | |
2014-02-04 | 2014-02-24 | Order Entry (Iteration 3) | JSS, KenyaEMR, OpenMRS | Wyclif Luyima | Google Hangout | Yes | Yes | |
2013-12-16 | 2014-02-03 | Order Entry (Iteration 1 & 2) | JSS, KenyaEMR, OpenMRS | Wyclif Luyima | Google Hangout | Yes | Yes | |
Reporting Sprint | James Arbaugh | Mike Seaton | No | Yes |
...
From | To | Topic | Leader | Developer Effort Estimated | Met Goals? | Designed Properly? | Kick Off Meeting? | Retrospective? | |
---|---|---|---|---|---|---|---|---|---|
March 28 | April 10 | All | 2 wks | Yes |
| ||||
Mar 14th | Mar 27th | Mike Seaton | 2 wks | Yes |
|
|
| ||
Feb 28th | March 13th | Community Development Swim Lane | 2wks | Yes |
|
|
|
| |
Feb 7th | Feb 27th | 3wks, 3D | Yes | Yes | Yes | Yes | |||
Jan 24 | Feb 6 | Joaquin Blaya, Mike Seaton | Daniel, Wyclif, Andrea, Mike, Rafal | Yes | Yes | Yes | Yes | ||
Jan 9 2013 | Jan 23 | Reporting Module: integrating with Calculation module, integrating with MDS, etc | 2 Weeks | Yes | Yes | Yes | Yes | ||
Dec 24 | Jan 8 | Rafal (spike) | Yes | Yes | No | No | |||
01/08/14 | 15/08/14 | Allergies (Iteration 1) | Jonathan Teich, Shasha Liu | Daniel Kayiwa | Yes | ||||
15/08/14 | 29/08/14 | Allergies (Iteration 2) | Jonathan Teich, Shasha Liu | Daniel Kayiwa | Yes | ||||
Dec 10 | Dec 24 |
| Yes | No | No | Yes | |||
November 22 | Dec 6 |
|
|
|
|
| |||
Nov 7 | Nov 20 | 2 weeks, Wyclif on Mockito | N/A | N/A | N/A | N/A | |||
October 24 | November 6 | 2 weeks, Wyclif and Daniel | N/A | N/A | N/A | Yes | |||
October 1 | October 21 | 3 weeks (Implementer Conference- Oct 9-12) |
|
|
|
| |||
September 17 | September 30 | 2 weeks, full team |
|
|
|
| |||
September 10 | September 16 | 1 week |
|
|
|
| |||
September 3 | September 9 | Spikes by Core Developers | 1 week, |
|
|
|
| ||
August 13 | September 2 | 3 weeks, full team |
|
|
|
| |||
July 30 | August 12 | 2 weeks, full team |
|
|
|
| |||
July 16 | July 29 | Rafal lead & Volunteers |
|
|
|
| |||
July 2 | July 15 | Daniel lead, but doesn't code |
|
|
|
| |||
June 18 | July 1 | Full team 2 week sprint |
|
|
|
| |||
June 4 | June 17 | Full team 2 week sprint |
|
|
|
| |||
May 21 | June 3 | Full team 2 week sprint |
|
|
|
| |||
May 7 | May 20 | 1 week, full team |
|
|
|
| |||
Apr 29 | May 5 | Order Entry Wk 2 | 2 core developers |
|
|
|
| ||
Apr 29 | May 5 | 1 week, Jer + core dev |
|
|
|
| |||
Apr 22 | Apr 29 | Atlas Module 1.0 - tickets |
| 1 core Developer |
|
|
|
| |
Apr 22 | Apr 29 | 2 core developers |
|
|
|
| |||
Apr 15 | Apr 20 | 1 week. Darius, Rafal, Roger, Saptarshi, ? |
|
|
|
| |||
Apr 15 | Apr 20 | Atom Feed Spike/Prep Wk 1 | 2 weeks, Ben only |
|
|
|
| ||
Apr 2 | Apr 15 |
|
|
|
|
| |||
Mar 26 | Apr 1 |
|
|
|
|
| |||
Mar 12 | Mar 25 |
|
|
|
|
| |||
Feb 27 | Mar 11 |
|
|
|
|
| |||
Feb 13 | Feb 24 |
|
|
|
|
| |||
Jan 30 | Feb 12 | Planning notes: Ben missing first week |
|
|
|
| |||
Jan 16 | Jan 29 | Planning notes: Ben missing second week |
|
|
|
| |||
Jan 2 2012 | Jan 15 |
|
|
|
|
|
...