Release Timelines for 2.3
Status | Activity | Resources Needed | Duration | Completion Date | Comments | |
---|---|---|---|---|---|---|
1 | COMPLETED | Agreeing the vision and strategic goal of the RoadMap activities | Community Core Ops Lead | Once a year | March 4th 2019 | |
2 | COMPLETED | Call out on all OMRS Communication channels announcing the commencement of the RoadMap planning Process | TPM | 1 week | March 15 2019 | |
3 | COMPLETED | Identification of volunteer team members for core activities of the group, such as release management, BA, QA , testing | TPM Community Implementers Individual contributors | Continuous | April 15 2019 | |
4 | COMPLETED | Receive new feature requests from community Prioritization and Validation of feature requests Confirmation of feature owners and resourcing to develop feature (or go it alone) | TPM Community Implementers Individual contributors GSOC?? | continuous (2-4 weeks window) | March 30 2019 | |
5 | STARTED | Commencement of Release Process | Release Manager, Community Dev's | 8-15 weeks | June 7th 2019 | August 31 |
STARTED | Quality Assurance & Testing | QA , Community, Community Dev's | 4-6 weeks | |||
7 | DONE | Application pushed for community alpha release (or criteria that meets an alpha release) | Release Manager, Community Dev's | 4-6 weeks | ||
8 | DONE | Beta Release | Release Manager, Community | 4-6 weeks | ||
9 | WAITING | Completion of Release Process & Application Launch | Release Manager | 4 weeks |
Release features/bug fixes
Feature | Description | Status | Point of Contact | Comments | |
---|---|---|---|---|---|
1 | REST resource for Creating Order Group | Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration. | DONE | Need to ask product owner if they are still interested in continuing @ Yusuf Akhond | |
2 | REST WEBSERVICES Adding ability to Search for Living Patients |
| DONE | ||
3 | REST WEBSERVICES Fix to enable retrieving of non-active patient encounters |
| DONE | ||
4 | REST WEBSERVICES Addition of DrugReferenceMapResource |
| DONE | ||
5 | Upgrade our libraries |
| DONE | Review of the palm file to better understand which libraries need upgrading; i.e. what libraries do we have and what is the latest for that version. We could write a maven command that can generate a report with libraries that need updating. From there we can determine what level of effort will be required to upgrade the library. | |
6 | Bundle addon manager owa |
| BEING TESTED | Need dev to do final testing. If we can find dev in the community, great; otherwise, Daniel will do. | |
7 | FHIR |
| DONE | ||
8 | Adopting OpenJDK |
| DONE | May need to get feedback from the community on whether they have used OpenJDK and whether it is stable enough Review the CI build to determine if it can run on OpenJDK | |
9 | Support for alternate authentication schemes |
| DONE |
| |
10 | Use of the new Implementation ID server URL, and support for redirects & https in the custom HttpClient class |
| DONE |
Project Updates:
- GitHub Link : https://github.com/openmrs
- JIRA Link : https://issues.openmrs.org
- Talk Forum Link : https://talk.openmrs.org
- OpenMRS Help Desk : https://openmrs.desk.com/customer/widget/emails/new?
Release Notes