Discussion items
Project Activities Spreadsheet
Item | Who | Notes |
---|
GSoC | | |
Internships: Andela | | - Pushing for an MVP to be released.
- Tentative release March 31 2019
|
Sync 2.0 (SolDevelo, Jembi) | | |
OpenMRS Reference Application 2.9 | | - Reuben Varghese will compile a blogpost regarding the release of 2.9. Still Pending
- New concept data updated.
- In discussions with Reuben Varghese to determine where he could need help to push the application to Beta release community testing
|
OpenMRS Platform 2.2 | | - Platform 2.2 is in beta release
- PIH has deployed this to a live implementation , therefore there is grounds to move from beta to full release
- Samuel Male to start Full release process
|
Technical Road Map /Strategic Operational Plan | | - Technical Roadmap 2019 (For Platform Currently)
- Platform features have now been finalized. Tentative Release Mentor Samuel Male for Platform 2.3 . Release manager to be announced in the next day or 2
- Estimate to complete this next platform release 9-12 weeks (June 7th)
- Ref App intro post has been made. Kaweesi Joseph will be the Release Mentor for Ref App. Release Manager TBD
|
Documentation Review 2019 GSoD 2019 | | |
PM tool |
| |
AOB |
|
|
Next week |
| Daylight Savings Time began on 10 March, which means this call with be one hour later for people observing DST beginning next week (e.g., 11am EDT / 8am PDT).
|
Action items