2019-06- 10 Project Management Meeting


  • Regrets


Discussion items

Project Activities Spreadsheet

ItemWhoNotes
GSoC

Internships: Andela

  • All tickets should be completed by the end of the week
  • OCL should be available for community testing from Monday June 17th
OpenMRS Reference 2.10
  • Reference Application 2.10 Release Management
  • Schedule a follow up meeting during community office hours on Wednesday Jun 12
  • Remove some of the bigger features from the release roadmap e.g. Datawarehouse as it warrants its own separate conversation
OpenMRS Platform 2.3
  • Platform 2.3.0 Release Management Page
  • To include
    Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.
    in the release notes . Already merged but should be noted.
  • OWA needs to be broken down into tickets that can be worked on by community memebers

Documentation Review 2019

GSoD 2019

  • More project details can be found here
  • Follow up with Burke and other mentors to ensure they are engaging with GSoD Applicants
Front Ends ProjectUpdates every 2 weeks

https://talk.openmrs.org/t/micro-frontends-architecture-for-openmrs/22557/17

PM tool

AOB

Updating Communication Channels on OpenMRS

Next week



Action items