20 min | Review timeline and plans for 1.10 and 1.11 | @Wyclif Luyima | Development of 1.10 is complete Alpha needs 1.11 to be reviewed during Developer call tomorrow, and will be able to make action items from there. How do we test the upgrade? Can we have PIH do a test against real data and refactor ordering Xray's for example to 1.10? @Darius Jazayeri will have a conversation with Bahmni to see if they can assist with testing of the upgrade progress. @Burke Mamlin will assist. "Now is the time to consider that it is stabilized and would be a good time to review. Testing Goals for the Alpha Closest real world testing capability is help an implementation get on the new API and possibly a certain module (order entry) providing them with help with the refactoring. Even if they don't plan on immediately upgrading to 1.10 we are asking you to try in a test environment that has patient data so that we can get feedback on the upgrade process.
|
10 mins | Review Action Items from Last Week's Meeting | @Chris Power | Take tickets from testing and press hard on testing and have tickets created to go into a support sprint. Need a more a directed effort - Burke suggestion Paul to talk to Andy K. about drug content - In progress
|
20 mins | New Topics | @Shasha Liu, @Chris Power | Resource Allocation Capacity planning Communication issues This is what we are working on now, if you are not interested in helping with that you can work on allergies... (example) Create a roadmap for the next thing or possibly the next two things. Have this happen on this call How do we get updates out on what's being worked on so that others can see how to become involved.
Governance model
|
Remaining | Open Discussion | | |