Release Timelines:

 

 

Status

Activity

Resources Needed

Duration

Completion Date

Comments

 

Status

Activity

Resources Needed

Duration

Completion Date

Comments

1

completed

Agreeing the vision and strategic goal of the RoadMap activities

Community

Core Ops Lead

Once a year

 

Still looking to identify a Lead from the community

2

completed

Call out on all OMRS Communication channels announcing the commencement of the RoadMap planning Process

TPM

1 week

March 22 2019

 

3

completed

Identification of volunteer team members for core activities of the group, such as release management, BA, QA , testing

 

TPM Community

Implementers

Individual contributors

Continuous

April 30 2019

 

4

completed

Receive new feature requests from community

Prioritization and Validation of feature requests

Confirmation of feature owners and resourcing to develop feature (or go it alone)

TPM Community

Implementers

Individual contributors

GSOC??

continuous

(2-4 weeks window)

March 30

 

5

ongoing

Commencement of Release Process

Release Manager,  Community Dev's

8-15 weeks

August 2019

 

6

completed

Quality Assurance & Testing

QA ,  Community, Community Dev's

4-6 weeks

 

 

7

Completed

 

Application pushed for community alpha release (or criteria that meets an alpha release)

Release Manager, Community Dev's

4-6 weeks

 

 

8

Completed

 

Beta Release

Release Manager, Community

4-6 weeks

 

 

9

Completed

 

Completion of Release Process & Application Launch

Release Manager

4 weeks

 

 

Roadmap Features

Ongoing talk post for roadmap planning

Feature

Description

Status

Point of Contact

Comments

Feature

Description

Status

Point of Contact

Comments

1

Implement Complete Condition List

Condition List

see Talk post

https://talk.openmrs.org/t/tracking-progress-of-the-condition-list-phase-gsoc-project/23400/2

COMPLETED

 

 

See tickets fixed

key summary type created updated due assignee reporter priority status resolution

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

 

 

 

 

GSoC 2019 project.  Worked on by @Haripriya Reddyand mentored by @Daniel Kayiwa and @Ellen Ball

2

Inclusion of Growth charts from CDC/WHO

https://talk.openmrs.org/t/growth-chart-in-refapp/21530

and 

https://talk.openmrs.org/t/we-need-a-ba-to-do-an-assessment-growth-charts-for-reference-2-10/23370/14

COMPLETED

Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.

See Ticket Board For Harvesting Features into Reff App 2.10  below

https://issues.openmrs.org/secure/RapidBoard.jspa?rapidView=210&view=detail&selectedIssue=RA-1602

 

 

 

see  current on going disccusion at https://talk.openmrs.org/t/defining-efforts-needed-to-include-growth-charts-in-the-reference-application/23278

It was concluded to create a new module for the Growth chart , because core_apps module is becoming to bulky.

see new module repo at https://github.com/openmrs/openmrs-module-growthchart

3

Bug fixes and modifications

We have a number of  Tickets that include bug fixes and feature enhancements in the reference Application .See the Ref-app 2.10 Tickets Board here https://issues.openmrs.org/secure/RapidBoard.jspa?rapidView=204

COMPLETED

See tickets fixed

key summary type created updated due assignee reporter priority status resolution

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

 

Community members called upon to work on these tickets

https://talk.openmrs.org/t/want-to-become-a-dev2-3/23277

4

Integrate Bootstrap as a foundation of Reference application

Read more about tht GSOC project at 

Integrate Bootstrap as Foundation for OpenMRS Reference Application

see talk post 

https://talk.openmrs.org/t/gsoc-2019-bootstrap-as-a-foundation-for-reference-application-ui-project/23162/81

Completed 

 

Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

Primary mentor : @Stephen Senkomago Musoke

Backup mentor:  @Juliet Wamalwa

Assigned to : @Ayeshmantha Perera

5

Improve Reference Application Performance

We need to optimize the performance of The reference Application by Revising the Current List of modules and removing some modules whose current usage is low

see talk thread https://talk.openmrs.org/t/reference-application-modules-review/25065

COMPLETED

Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

@Cynthia Antwi

@Daniel Kayiwa

6

Additon of More FonteAwesome 5 Icons

https://talk.openmrs.org/t/upgrading-font-awesome/23910

COMPLETED

Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

@Haripriya Reddy

7

Update Reference Metadada Packages with Covid-19 Concepts

https://talk.openmrs.org/t/covid-19-concept-metadata-package-for-reference-application-2-10/27734

COMPLETED

Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.

 

@Moses Mutesasira

Project Updates:

Release Notes