GSoC 2012 Plan

Done

Iteration 1 : May 21 - June 7

Effort

Refactor current module into new Maven archetype.

High

Create unit tests for existing HR module classes

High

Iteration 2 : June 8 - June 15

 

Move existing HR Module pages to new role based home page for HR module

Low

Iteration 3 : June 16 - July 8

 

Create services

Moderate

 

 

Create UI pages for new functionalities

Moderate

Buffer

 

Iteration 5 : Aug 2 - Aug 15

 

Redesign installation process to install HR tables and, if desired, test data, and to collect required configuration data.

High

Documentation

Moderate