GSoC 2012 Plan
Done
Iteration 1 : May 21 - June 7 | Effort |
Refactor current module into new Maven archetype. | High |
Create unit tests for existing HR module classes | High |
Iteration 2 : June 8 - June 15 |
|
Move existing HR Module pages to new role based home page for HR module | Low |
Iteration 3 : June 16 - July 8 |
|
Create services | Moderate |
|
|
Create UI pages for new functionalities | Moderate |
Buffer |
|
Iteration 5 : Aug 2 - Aug 15 |
|
Redesign installation process to install HR tables and, if desired, test data, and to collect required configuration data. | High |
Documentation | Moderate |